Specifications include, but are not limited to: 40-05 MAINTENANCE OF TRAFFIC ADD the following: The contractor shall be responsible for cleaning and maintaining all terminal and airport access roads and use a pick-up type sweeper on all pavements and adjacent pavements utilized during the construction process when material is tracked onto the existing pavement. The Contractor shall have a sweeper on site and maintain all pavements clear of dirt and debris at all times or as requested by the Resident Engineer. If the Contractor fails to comply with the Standard Specifications, Contract Plans or these Special Provisions concerning traffic control, all construction activities shall cease and the Contractor will be required to correct the deficiencies to the satisfaction of the Resident Engineer and Owner. The Contractor shall be responsible for supplying, maintaining and moving all barrels and/or barricades required for the staged construction as shown and detailed in the contract plans. Work on or near runways will not be permitted. 40-09 AIRPORT OPERATIONS DURING CONSTRUCTION ADD the following: The Contractor shall maintain operation to the JW Aviation Flight School at all times, and shall operate within phased areas as detailed in the contract plans at all times. The storage and parking of equipment and materials shall be within the phased delineated areas at all times, unless otherwise directed by the Resident Engineer. Open trenches, excavations and stockpiled material near operation pavement shall be protected. The work area shall be kept clean of debris and garbage that may become airborne and deposited on the nearby runways. To help facilitate this effort garbage barrels shall be provided by the Contractor for use of the workers during construction.