Specifications include, but are not limited to:. Proposal will include all parts and labor to complete the following: 1.E-85 dispenser removal and blow back product line 2.Remove 10' x 10' area of existing hard surface at E-85 STP sump and 7' x 8' area at island to facilitate sump replacement 3.Remove existing conduits from sumps without damage to wires, existing wire to be re-used. 4.Disconnect product lines at both ends and remove sumps. 5.Install new STP and dispenser sumps on E85 product, install existing STP in new sump, plumb STP and dispenser sumps and air test product line. 6.Hydro test sumps and air test product lines with State Fire Marshall 7.Backfill excavation areas and pour back concrete to match existing pavement section. 8.Vac excavation of STP sump in tank area is included in this quote to avoid any potential damage to product of electrical lines.