Specifications include, but are not limited to: Concrete Street Reconstruction on Eastview Terrace – Charlotte St. to 124. Eastview Terrace. Areas that will need increased traffic control include: North Ave. and Main St. Southbound lane ~ 3 panels 100 sq. yd. Finley Rd. and 22nd St. Intersection ~ 103 sq. yd. of panels and ~ 50 sq. yd. Eastbound lane of 22nd. St. At 22nd St. and Westview ~ 3 panels 80 sq. yd. And Class B Patching located throughout the Village of Lombard. This work consists of the removal of approximately 1,000 SQ. YD. of PCC Pavement with monolithic curb and replacing with approximately 1,000 Feet of B.6.12 curb and gutter and 1,000 SQ. YD. of High Early Strength PCC Pavement 8 Inch Jointed, removal and replacement of approximately 1,700 Sq. Ft. of PCC Sidewalk 5” and approximately 6,700 Sq. Yds. Of Class B Patching type IV 8” and 10”, as well as all other incidental items needed to complete the project.