This project has had cleanouts added recently in the middle of the sewer lateral. The sewer replacement will start from the new cleanout midway in the lateral to the main under 37th Street. There are two existing trees that are along this pathway that will be removed before the work will begins. Replace all the existing line from the clean out to the main with new PVC. Use approved saddle to tie in PVC to the main. If the old connection has to be abandoned then appropriate patch on the main will be required with concrete around the patch. The PVC line must be fully supported in undisturbed soil or compacted rock along the trench for the length of the new line. Inspection will be needed once connections have been made before back filling. The back fil will need to be fill sand and compacted in lifts leaving 12” for top soil. The yard will be graded and seeded when the projects finished. Any sections sidewalk taken out will need to be replaced. The street, curb, and gutter taken out shall be replaced blended back in to existing.