This project has had a new sewer lateral ran to the edge of the street. The previous sewer replacement will need a new cleanout added in the lateral within 5โof the house. Replace all the existing orangeburg from the edge of the street out to the main with new PVC. Use approved saddle to tie in PVC to the main. If the old connection has to be abandoned then appropriate patch on the main will be required with concrete around the patch. The PVC line must be fully supported in undisturbed soil or compacted rock along the trench for the length of the new line. Inspection will be needed once connections have been made before back filling. The back fil will need to be fill sand and compacted in lifts leaving 12โ for top soil. The yard will be graded and seeded when the projects finished. Any sections sidewalk taken out will need to be replaced. The street, curb, and gutter taken out shall be replaced blended back in to existing.