Execution: 1. Verify all elevations and measurements before submitting quotes. 2. Call JULIE before you dig! 3. Place traffic control as needed. No open excavations may be left when contractor is not on site. Excavations must be covered, and fencing/handrail maintained. Provide fencing and /or security to prevent vandalism. Any vandalized concrete shall be repaired or replaced at Owner’s discretion. 4. Excavate surrounding area as needed. 5. Place forms for lower concrete footing and inspect for debris or standing water before pouring. 6. Place secondary forms for reinforced foundation, inspect for debris or standing water before pouring. Place reinforcement per Section 2 and 3 of attached foundation plans. 7. Chamfer exposed edges, 3/4” x 3/4” minimum. 8. Exposed surfaces need to have a rubbed finish. 9. Backfill and compact. 10. Clean soil, refuse, and debris from area before removing traffic control. 11. Any damage to the surrounding walkways or landscape will be the responsibility of the contractor to rectify at their expense