Specifications include, but are not limited to: The removal of the Upper Plant access hatches/covers, take and record the runner blades measurements, isolate governor, remove, dispose of and refill hydraulic oil from runner and governor, remove dispose of and refill the bearing lube oil, remove the top half of the discharge ring, disconnect the oil piping, remove runner hub, disassembly of runner and runner hub, rebuild/reassembly of the runner hub with new bushings, seals, wear parts and other parts needed to shop test runner hub, reinstall a pressure tested and functioning runner hub, reconnect oil piping, refill oil, reassemble top half of discharge ring, take and record as installed blade runner measurements, reinstall access hatches/ covers and provide support during the start up and commissioning of the unit. The bid will include all equipment, materials and labor to complete the project.