Phase 1 – Pre-Construction • Connect temporary fire trailer to supply per attached drawing below • Connect temporary fire trailer to fire loop – outage TBD • Blank off un-used connections for construction • Contractor to provide all material Phase 2 – Demo • Determ and pull back wiring to electrical components – Contractor to clearly mark and label all connections o 4160 V Motor starter/Controller o Alarm Panel o Lights, fan, heater, etc. o Jockey pump o Transformer and associated circuits o Diesel engine controller o Diesel engine o Diesel engine starting batteries o Verify conductor usability for new construction • Remove electrical equipment and stage in FMPA warehouse – Contractor to mark and label all components as needed for re-assembly o Control Panels o 4160V motor starter o 480v transformer o Diesel Engine Batteries o Space heaters and controllers • Remove mechanical equipment and stage in FMPA warehouse o Diesel Pump and engine assembly (Can be disassembled) o Electric pump and motor assembly (Can be disassembled) o Jockey pump o Diesel fuel tank – FMPA to empty but not clean o External ladder for fuel tank filling (unbolt for re-use) o Engine silencer on roof o Valves o Flowmeters o Check valves