Specifications include, but are not limited to: The project includes replacement of the sawn lumber pieces and the replacement of select Prestress-precast (PSPC) beams. The work on the pier will include to remove and replaced deck boards, guard rails [top, mid and toe boards], guard rail posts, the removal of (4) Prestress precast beams and the replacement with glulam beams. The nailers attached to the top of the existing concrete beams will need to be replaced if found to be decayed once exposed. The new deck boards will have an additional runner placed along the bottom at midspan between each beam to control deflection. The approach boardwalk work will include to remove and replace the walk-boards, the guard rails [top, mid and toe boards], guard rail posts and to replace piles that are found to be depleted once they are exposed.