Specifications include, but are not limited to: 4.1.1 Demolition 1. Deliver 40 yard dumpster to site. 2. Demolish and discard all lockers in the center areas of both locker rooms. 3. Diamond and sand complete floor tiles in both locker rooms to remove existing coating and prep surface. 4. Fill any cracks fill voids using hydraulic. 5. Apply one coat of primer to complete flooring. 6. Apply one coat of general polymer with flakes, 1/8” in both areas. 7. Apply one coat of sealer with non-skid additive to complete flooring cove base. 8. Touch-up any damage to walls. 4.1.2 New Construction: Flooring for 3,000 Sq. Ft. 1. Fill grout joints. 2. Apply base coat 4408 as top coat. 3. Apply GP3569 flakes. 4. Apply GP3569 clear as sealer. 5. Install 220 square feet of cove base.