Specifications include, but are not limited to: 1) Drilled Shafts: • Process and review the Drilled Shaft Installation Plan in accordance with CPAM. • Schedule a pre-drilled shaft installation meeting to go over the drilled shaft installation procedures. Make sure the Contractor’s drilled shaft field superintendent(s), Concrete QC technician(s), CEI drilled shaft inspector(s), representative of Turnpike Concrete Group, and the DGE are invited. Prepare and distribute meeting minutes to all the attendees. • Inspect installation of test holes (methods shafts), load test shafts, and production shafts and ensure they are constructed in accordance with the plans, specifications, and special provisions for the Construction Contract. Report to the DGE any problems observed during the installation of any drilled shaft, deviations from the Drilled Shaft Installation Plan or contract documents, and construction quality issues associated with the Contractor’s methods.