This contract also includes, but is not necessarily limited to, all labor, materials and equipment for the following: 1. Provide water and air testing and balancing of HVAC systems. The contractor shall prepare, at a minimum, a preliminary balance report for the City of Wilmington Final Inspection. 2. Provide water testing and balancing of plumbing systems. 3. This contract includes all Division 0 and Division 1 General Requirements. All commissioning requirements are identified in Division 1 and are a requirement of this contract. 4. Submissions will be reviewed once, and any resubmittals will be reviewed once. Any other submittals will be billed to the contractor at the Engineers standard rates. Please thoroughly review all submissions prior to forwarding to avoid these costs. 5. Provide complete signed and sealed testing report prior to substantial completion and final inspection as required by New Castle County.