Specifications include, but are not limited to: A contractor to expand the Rehab Department at The Nathaniel
Witherell (TNW). I. File for building permits with all applicable government agencies.
2. Conduct a pre-construction meeting with TNW, contractor and team. Contact CallBefore-You-Dig
regarding foundation work. Pre-construction meeting to include
discussions on required permits and inspections, as well as a list of required inspections
and an inspection schedule.
3. Field stake out the limits of all activities and install, at a minimum, a snow fence along
construction limit lines along environmentally sensitive and tree protection areas, as
required by all agencies.
4. Safe off all utilities within the bounds of the construction site, ensure Call Before You
Dig has visited the site.
5. Demolish existing greenhouse structure and existing masonry wall as noted on site plans.