1 General Conditions – includes but not limited to, mobilization, demobilization, project manager, superintendents, laborers, office support staff, temporary protection, dust protection, safety, dumpsters, permit fees, fencing, signs, and includes overhead & profit. $ 2 Div. 3 Concrete includes but not limited to, all work associated with concrete slabs on grade as required per plans. $ 3 Div. 4 Masonry Fireplace structure includes but not limited to, all work associated with masonry as required per plans for the Fireplace structure. $ 4 Div. 4 Masonry Fire Pit includes, but not limited to, all work associated with masonry as required per plans for the Fire Pit. $ 5 Div. 5 Structural Steel Framing, Metal Decking, & Metal Fabrications includes but not limited to, all work associated with all steel framing, decking & metal fabrications on grade as required per plans. $ 6 Div. 5 Metal Stairs includes but not limited to, all work associated with metal stairs as required per plans. $ 7 Div. 6 Wood & Plastics & Rough Carpentry & Finish Carpentry – includes but not limited to, all work associated with Wood & Plastics & Rough carpentry & Finish Carpentry work as required per plans. $ 8 Division 6 – Deck Construction – includes but not limited to all work associated with the construction of the exterior deck overlooking the pond. $ 9 Div. 6 Heavy Timber Construction – includes but not limited to, all work associated with heavy wood timber trusses work as required per plans. $ 10 Div. 6 PVC Decking – includes but not limited to, all work associated with PVC decking work as required per plans. $ 11 Div. 7 Thermal & Moisture and Roofing & Accessories – includes but not limited to, all work associated with thermal & moisture work as required per plans. $ 12 Div. 8 Doors & Windows – includes but not limited $ to, all work associated with doors & windows work as required per plans. 13 Div. 8 Alum Curtain Wall & Curtain Wall Glazing – includes but not limited to, all work associated with curtain wall work as required per plans. $ 14 Div. 9 Finishes including Gypsum Board– includes but not limited to, all work associated with gypsum board as required per plans. $ 15 Div. 9 Finishes including Tiling– includes but not limited to, all work associated with tiling as required per plans. $ 16 Div. 9 Finishes including Resilient Flooring & Carpet Tile– includes but not limited to, all work associated with resilient Flooring & carpeting as required per plans. $ 17 Div. 9 Finishes including Painting– includes but not limited to, all work associated with painting as required per plans. $ 18 Div. 10 Specialties including toilet compartments, toilet accessories, fire extinguishers & flagpole - includes but not limited to, all work associated with specialties as required per plans $ 19 Div. 10 Specialties including Operable Partition - includes but not limited to, all work associated with Operable Partition as required per plans $ 20 Div 12 Furnishing - including motorized & manual window shades $ 21 Div. 21 Fire Suppression - includes but not limited to, all work associated with Fire Protection system & equipment work as required per plans. $ 22 Div. 22 Plumbing - includes but not limited to, all work associated with plumbing work as required per plans. $ 23 Div. 23 Heating Ventilating and Air Conditioning - includes but not limited to, all work associated with HVAC work as required per plans. $ 24 Div. 26 / 28 Electrical & Fire Alarm – includes but not limited to, all work associated with electrical, fire alarm and associated work as required per plans. $