A. Scope of work consists of installation of materials to be furnished under these Specifications and without limiting generality thereof consists of furnishing labor, materials, equipment, hoisting, plant, transportation, rigging, staging, appurtenances, and services necessary and/or incidental to properly complete all electrical work as shown on drawings, as described in the Specifications or as reasonably inferred from either as being required in opinion of the Architect and Engineer. B. The work shall include, but is not limited to: 1. Demolition. 2. Temporary power. 3. Installation of Owner Furnished temporary transformer and load interrupter switch. 4. Medium voltage load interrupter switches. 5. Medium voltage substation transformers. 6. Medium voltage feeders. 7. Medium voltage terminations and splices. 8. Light fixtures. 9. Switches and receptacles. 10. Branch circuit wiring. 11. Reinforced concrete pads. 12. Precast reinforced concrete foundations for site lighting standards. 13. Chain link fencing