The Project generally consists of providing necessary labor, equipment, and materials for the application of 1” thick asphalt overlay (HMA C2 ½” PG 64-16), wedge cold-milling, shoulder grading, adjustment of driveway approach entrances, and removal and installation of thermoplastic striping and pavement markings on various street segments within the Town of Apple Valley as specified in the Technical Specifications and as directed by the Town Engineer. Work on the Project shall be completed within forty (40) Working Days. The anticipated award date is February 11, 2025, and the anticipated start date is on or about March 3, 2025. Please note that portions of the work will be adjacent to school properties. Contractor will coordinate with Town staff to minimize the impact to school traffic. Scheduled closures for Spring Break are as follows: (March 17-21, 2025 for Desert Knolls Elementary on Symeron Road, and Mariana Academy on Manhasset Road (AVUSD), and on March 24, 2025 – April 4, 2025 for A.A.E. Charter School, on Mana Road.