Specifications include, but are not limited to: A) Coordinating delivery of the new Articulated Slope Revetment (ASR) which will be provided to the contactor as owner-furnished material. This material will be furnished by the CITY because of the long-lead time for fabrication and short construction window. B) Temporary removal of chain link fencing and /or metal guard rail to provide construction access. This material will be reinstalled near the end of construction. C) Constructing a stream by-pass. D) Removing the temporary rock slope protection and fabric which was placed in 2017. E) Excavation and shaping the channel subgrade. F) Furnishing and installing crushed rock, geogrid and rock slope protection fabric. G) Installing galvanized “eyes” in channel wall to connect the ASR.