Specifications include, but are not limited to: •Remove drywall from the walls, and ceiling in the offices on the first floor (approx. 350 s/f of 5/8" drywall). •Remove and replace Shower-Pan and check for leaks in the second-floor bathroom. •Remove and replace damaged plywood flooring as necessary (Approx. 48 s/f.). •Remove and replace bathroom flooring if needed. •Remove window for ventilation and provide dust control. •Perform mold remediation for the exposed areas if necessary. •Purchase and install new 5/8"drywall for fire walls, and existing walls as necessary. •Paint and patch bathroom and two offices. •Test new shower drain and check copper plumbing and shower valve. •Contractor shall remove all demo. Material from job site. Clean-up construction debris and remove from job site. •Ensure safety is observed at all times. •Any electrical work must adhere to NFPA 70E.