The work generally consists of: 1. Mobilization including site access, preparation of construction staging areas, temporary fencing, preparation of submittals, protection of assets and other preparation activities. 2. Compliance with all permit conditions, including sediment and erosion control, dust and noise control, and wildlife and environmental protection throughout construction. 3. Installing protection fencing and signage. 4. Protecting all existing pavements, signs, stairs, etc., for vehicle and pedestrian traffic, and protecting the rock revetment, rock breakwater, and utilities, including storm drainage, and temporarily removing and replacing existing stairs. 5. Installation of navigation beacons and buoys to denote areas of navigation encroachment. 6. Installation of temporary construction access for equipment. 7. Harvest eelgrass from Mitigation Area and transplant in the Secondary Transplant sites. 8. Hydraulically or mechanically dredge sand from East Basin Areas 1B and 1C and mechanically place in Mitigation Fill Area to form bed for eel grass planting. 9. Harvest eelgrass from East Basin Area 2 and plant in Mitigation Area. 10. Hydraulic dredging of Areas 1A and 2 and placement of dredged sediments at Surfers Beach, including constructing sand containment berm and finish grading with land-based equipment, and discharge water control. 11. Surveying and calculations for measurement, payment and acceptance. 12. Pedestrian and vehicular traffic management (on land and in water). 13. Site cleanup, repair of any damages, restoration and demobilization.