The work to be done consists of furnishing all materials, equipment, tools, labor, and incidentals as required by the Contract Documents, Specifications and Plans for the above stated project. In general, the project consists of work at two sites as follows: The Snipes Park Booster Station (Station) Upgrades work will include constructing a hydropneumatic tank with appurtenances, foundation, and associated piping; upgrading the pumps in the existing packaged booster station; control upgrades; and site improvements including retaining wall, tubular steel fencing, curb and gutter, resurfacing existing pavement, and placing new pavement. The Lake Norconian Flow Control Station (FCS) work will include demolishing the existing below grade manually operated hydraulic control valve and vault, and constructing a new above grade FCS including solar power system, electronically operated hydraulic control valve, telemetry controls, piping, isolation valves, sunshade, site fencing, and site work.