This update is to post the Bod Abstract from bid opening 30 May 2025.
This update is to add and additional RFI Q and A- After reviewing the updated RFI responses, could you please clarify if third party WQM is required at the DMPS AND the Dredge Site (In water), or is the third party requirement just at the DMPS? ---The 3rd party is required at both the DMPS AND the Dredge Site (In water).----See attachment Sacramento RFI Q-A_23 May 2025-
This update is to correct the response for Question 3 from Not require to IT IS required to be done by a 3rd party. Question and Answer 4 was added - Can a Dredging Plant and Equipment Schedule be updated from Richmond Inner Harbor Dredging Project Sacramento DWSC Dredging. Answer Strike though the Richmond Inner Harbor Dredging Project-replace with Sacramento DWSC Dredging. SEE ATTACHMENT Sacramento RFI Q-A_21 May 2025.
This update is to add SECTION 01 57 19 to Question 3 of the Q&A Attachment.
THIS UPDATE IS TO PROVIDE A LIST OF QUESTIONS AND ANSWERS- SEE ATTACHMENT -Sacramento RFI Q-A. PLEASE EMAIL james.neal@usace.army.mil with email addresses to be added the TEAMS Bid Opening by 13:00 30 May 2025 PDT
This acquisition is proceeding as a Full and Open Competition, Invitation for Bid (IFB). This Procurement will be conducted under FSC CODE: Z1KF, NAICS Code: 237990. The size standard for this code is $37,000,000. All questions should be directed to Dennis Neal: james.neal@usace.army.mil Estimated Cost Range is between more than $1,000,000 - $3,000,000. The work includes annual maintenance dredging of the Sacramento DWSC to -30-ft (MLLW) plus 1-ft of paid over-depth. All dredge material is suitable for the upland beneficial reuse sites listed in Specification Section 00 10 00 PRICING SCHEDULE AND requirements in specification Section 01 11 00 SUMMARY OF WORK. Dredge material may be suitable for beneficial reuses at Contractor furnished sites in accordance with the permit requirements of the specific reuse site.