The work is comprised of providing a submersible turbine pump in an existing 35-foot deep vertical raw water intake facility, and pipeline tie-in to the District’s existing raw water supply line near the District’s raw water intake facility at the Nacimiento River. The Work includes setting of the submersible turbine pump at the intake facility, installing associated instruments and appurtenances including, but not limited to, a pressure transducer, propeller flow meter, and air-vacuum valve, installation of aboveground piping and valves, installation of a 4” ductile iron pipeline, tie-in at the existing HRCSD Pump Station #1, electrical improvements, and all other work to make the vertical raw water facility complete and functional as specified, and as specified herein and as shown on the Contract Documents.