Furnishing all labor, materials, equipment tools, and services required to provide power to back at RTP as follows: • Provide and install new 18’x18’x10’ SS weatherproof enclosure capturing existing spare 2” at concrete slab edge. • Provide trench for 1 - 2” PVC sch. 40 conduit (min. 24” depth, red dye slurry and underground warning tape) from new enclosure to first pole location • Road cut section will require patching • Dig, provide and set 6 EA 30’ wood poles • Provide and install pole anchor kits at first and last pole • Provide and install 2” GRC risers up first and last pole with weather-head • Provide and install 10kvA 480v to 120/240v 1 PH Nema 3R mini load center with 50A main breaker • Provide and install mini load center on Pressure treated backboard and posts • Trench, provide and install 2 EA 1” PVC sch 40 stub out spares (10’ ea.) • Provide and install #4 3/c Aluminum triplex cable from pole to pole • Provide and install 3/c #4 THWN from existing MCC breaker to first pole • Provide and install 3/c #4 THWN from last pole to mini load center • Make all terminations and test.