****See Revised PWS and Amendment 1***
***See Questions and Answers Attached****
The project consists of the application of two coats of hot rubber sealant to existing asphalt paved surfaces and application of paint stripping for parking stalls, traffic lines, and ADA accessible areas.
Please see attachments:
1. Solicitation
2. PWS
3. Wage Determination
A site visit has been set up for 14 January 2026 at 10:00 AM PST. Contractors must have valid ID. All will meet at the operations office Address: Pine Flat Dam & Lake, 27295 Pine Flat Road Sanger, CA 93657. POC for the site visit is LaVerne Adams 559-792-6125. We encourage everyone to show up at least 15 minutes early to check in. Once the time for the site visit begins we will go into the site.
All questions must be submitted by email to the POC shown in the SAM.Gov posting NLT 15 January @1100 AM Pacific Time.