0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM 0002 080060 LEVEL 2 CRITICAL PATH METHOD SCHEDULE LS LUMP SUM 0003 090100 TIME-RELATED OVERHEAD (WDAY) WDAY 150 0004 090200 DISPUTE RESOLUTION ADVISOR ON-SITE MEETING EA 5 0005 090207 HOURLY OFF-SITE DISPUTE-RESOLUTIONADVISOR-RELATED TASKS HR 20 0006 090214 SAFETY QUALITY CONTROL MANAGER LS LUMP SUM 0007 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM 0008 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM 0009 120120 TYPE III BARRICADE EA 4 0010 120152 TEMPORARY PAVEMENT MARKING (TAPE) SQFT 34 0011 120165 CHANNELIZER (SURFACE MOUNTED) EA 77 0012 017517 TEMPORARY BARRIER SYSTEM (MASH TL-3) LF 1,260 0013 128652 PORTABLE CHANGEABLE MESSAGE SIGN (LS) LS LUMP SUM 0014 129108 TEMPORARY CRASH CUSHION TL-3 EA 8 0015 130100 JOB SITE MANAGEMENT LS LUMP SUM 0016 130201 WATER POLLUTION CONTROL PROGRAM LS LUMP SUM 0017 130640 TEMPORARY FIBER ROLL LF 4,980 0018 130730 STREET SWEEPING LS LUMP SUM 0019 130900 TEMPORARY CONCRETE WASHOUT LS LUMP SUM 0020 141120 TREATED WOOD WASTE LB 8,000