The winter storms of 2022/2023 damaged an existing perched culvert running underneath Prospect Road, which is an approximately 10-foot-wide traffic-rated, multi-use asphalt road. The erosion around the 55-foot long, 4-foot-wide corrugated metal pipe (CMP) triggered a slope failure washing out a 10-foot section of the culvert, culvert headwall, and portions of the creek bank. The scope of work includes replacement of those elements and added defensible measures, such as extending the culvert pipe to its original length, constructing a new headwall/footing, AC road repair above the culvert, and embankment stabilization.
TENTATIVE PROJECT SCHEDULE
April 30, 2025 Request for Bids issued
May 9, 2025 Mandatory Pre-Bid Meeting, 10:00 a.m. RSVP is Mandatory and must be completed by 4:00 p.m. on May 8, 2025.
May 13, 2025 Mandatory Pre-Bid Meeting, 10:00 a.m. RSVP is Mandatory and must be completed by 4:00 p.m. on May 12, 2025.
May 15, 2025 12:00 p.m. – Deadline for Bidders to pose questions.
May 21, 2025 12:00 p.m. – Final Addendum to Bid Package issued
May 28, 2025 Bid Opening, 11:00 a.m. 5050 El Camino Real, Los Altos, CA, 94022
July 9, 2025 Award of Contract by District Board of Directors Regular Meeting, begins at 7:00 p.m.
July 23, 2025 Anticipated execution of contract and written notice to proceed
July 28, 2025 Pre-Construction Meeting and deadline to submit Labor and Materials Payment Bond, Performance Bond, Proof of Insurance, and signed Agreement
August 11, 2025 On-site activities are anticipated to commence
October 31, 2025 Work on site complete
November 2025 Project Close Out