Specifications include, but are not limited to:removal of approximately 4,300 linear feet of taxiway pavement and the construction of approximately 4,500 linear feet of taxiway pavement in a new location. The scope of work generally includes the removal of approximately 17,400 SY of concrete pavement, 2,300 SY of asphalt pavement, and 8,800 SY of combination asphalt/concrete pavement and removal of the associated existing lighting infrastructure; approximately 27,000 CY of earthwork excavation; construction of approximately 36,600 SY of concrete pavement and 21,400 SY of asphalt shoulder; and installation of the associated taxiway edge lighting, centerline lighting, runway guard lighting, guidance signs, wind cones, and the airfield electrical lighting infrastructure, power utility infrastructure, and FAA communications infrastructure as shown on the plans and indicated in the specifications.