Specifications include, but are not limited to: General description for FY19-20: Improvements are required to some of the wall surfaces within the community. Contractor shall visit the site to evaluate which spans of the wall require surface repair. This bid includes surface repair and paint for a portion of the common wall surfaces shown on the Wall Plans as provided. The primary bid is for only the portions of the walls that require surface repair. Primary bid is to paint the surface repaired walls from pilaster to pilaster to avoid “patched” look. Contractor to provide bid add alternate to paint entire wall. 1) BID INSTRUCTIONS; CONTRACTOR SHALL PERFORM AND PROVIDE THE FOLLOWING: Contractor shall visit site to evaluate which spans of the walls require surface repair. PRIMARY BID shall be the surface repair of the walls shown in this plan set and as described herein only. PRIMARY BID shall include paint for the spans that required repair only. BID ADD ALTERNATE; Contractor shall provide a bid alternate to paint the entire wall shown on this plan set. Note that lengths as shown are provided for reference only. Contractor is responsible for visiting site to calculate actual lengths. The Town of Gilbert expects that the bid will ensure surface repair of only walls that 1) have peeling stucco or require filler and; 2) that are a part of this plan set; and that they will be repaired as described below. 2) ALL WALL TYPES; CONTRACTOR SHALL PROVIDE THE FOLLOWING FOR THE SPANS OF WALL ONLY THAT REQUIRE SURFACE REPAIR: 2’ from edge of wall, pull back decomposed granite prior to wall maintenance work. After wall maintenance work has been completed and approved by the Town of Gilbert, replace decomposed granite back to the edge of the wall. Trim back all homeowner vegetation/ trees that are overhanging wall. Trimming methodology shall be approved by the Town of Gilbert prior to commencing work. Trim back all common area vegetation that is impeding wall maintenance work. Trimming methodology shall be approved by the Town of Gilbert prior to commencing work. Caulk/ fill all cracks that are larger than hairline in size so no cracks are visible at completion. Wall locations/ types are being shown on the Wall Maintenance Bid Documents for reference only. Actual quantity of work shall be verified on site prior to bid. The contractor shall furnish all material necessary to complete work as shown on plans. 3) STUCCO WALLS THAT REQUIRE SURFACE REPAIR; CONTRACTOR SHALL BID THE FOLLOWING: Power wash entire wall surface. Remove stucco where it is peeling away from the CMU block surface. Apply Dunn Edwards or Sherwin Williams moisture barrier where CMU block is exposed. Substitutions are not permitted. Apply stucco to match existing where CMU block is exposed. Apply two coats of paint to repaired wall. Paint to be Dunn Edwards, or Sherwin Williams; substitutions are not permitted. Paint shall not be altered in any way or watered down. Color to match the existing stucco color. Contractor shall provide an 8’ long sample color for approval by the Town of Gilbert prior to painting the entire wall. Note that walls with a split face band shall be painted two colors; 1) grey band to match existing, 2) cream to match stucco. 4) INTEGRAL COLOR (INTERIOR) WALLS THAT REQUIRE SURFACE REPAIR; CONTRACTOR SHALL BID THE FOLLOWING: Power wash entire wall surface. Apply Dunn Edwards or Sherwin Williams block fill. Substitutions are not permitted. Apply two coats of paint to repaired wall. Paint to be Dunn Edwards, or Sherwin Williams; substitutions are not permitted. Paint shall not be altered in any way or watered down. Color to match the existing stucco color. Contractor shall provide an 8’ long sample color for approval by the Town of Gilbert prior to painting the entire wall.