Specifications include, but are not limited to: A. Receive Owner Furnished materials including three (3) each diesel engines and two (2) each module structures. See Section 01 64 00 – Receipt of Owner Furnished Materials. B. Provide a secured construction shop and yard for power plant module assembly. Provide temporary power, lighting, and heat as required. Note that after installation of the switchgear, heat shall be provided to maintain the control room above freezing. C. Place the module on cribbing as required make floor level within 1/4” throughout. Shim and re-level as required throughout the duration of construction. Cover the module and openings as required to prevent the entry of water. D. Furnish and install generation equipment, controls, mechanical equipment, piping, electrical equipment, wiring, raceways, instrumentation, and all other materials as required to provide a complete, fully functional power plant in accordance with the Contract Documents.