In general, the Work under this Contract includes, but is not necessarily limited to, the following major items as specified in these documents and as shown on the Project Map. The following descriptions are provided as an outline of major work items and shall not be construed as an inclusive or complete listing of all Items of Work under this Contract. This RFP is for hydroseeding only. All soil has been placed, graded, and track walked. Seed and fertilizer are provided and will be on site. Please see attachment B for the seeding map. This area is across the Nome Creek crossing. The contractor will be required to cross Nome Creek to complete this work. All permits associated with the work will be completed by Salcha Delta Soil and Water Conservation District (SDSWCD) and or BLM prior to starting work. The contractor must provide a HMCP (See Section 642).