EIE488 - REPLACE GENERATORS AT CHPP, EIELSON AIR FORCE BASE, ALASKA DB PHASE 1 RFPNAICS: 236220 SIZE STANDARD $45M 8(A) COMPETITIVE BEST VALUE TRADE OFF SOURCE SELECTION8(A) SET ASIDE SBA REQUIREMENT # - LK1742938112Q DESIGN AND REPLACE THE EXISTING FOUR 1,500 KW STANDBY GENERATORS AND ASSOCIATED ELECTRICAL EQUIPMENT THAT PROVIDE PRIMARY POWER TO THE EIELSON AIR FORCE BASE (EAFB) POWER PLANT BUILDING B6203. THE TWO BULK FUEL STORAGE TANKS ARE TO REMAIN BUT ARE REQUIRED TO BE INSPECTED AND A STATUS REPORT PROVIDED, DETAILING ANY CONCERNS, ISSUES AND DEFICIENCIES. THE BULK FUEL TANK FUEL GAUGE EQUIPMENT IS NOT FUNCTIONING AND MUST BE REPLACED. THE SIGNAGE FOR THE GENERATORS AND BULK FUEL STORAGE TANKS MUST BE REPLACED.