In general the work consists of the fourth phase of the Falcon Center for Health, Education and Wellness project. This phase will demolish the Nelson Center building. The Work will include relocation of a sanitary and storm sewer pipes under the Nelson Center building and removal and termination of all building utilities. Foundations and basement floors will be completely removed. The demolition will expose a basement wall of the adjoining May Hall building, which will remain, and this wall is to be patched and dampproofed. The excavated cavity will be filled to provide suitable subgrade for new construction. The contractor shall coordinate their work with the construction of a new addition to May Hall which will be performed under a separate contract. Construction of the May Hall addition will follow immediately after substantial completion of the Nelson Center demolition work.