Specifications include, but are not limited to: . 70th St.(WT410190621), W. Arthur Av. to W. Kinnickinnic River Pkwy.(77 working days); S. 71st St.(WT410190622), W. Arthur Av. to W. Dakota St.(64 working days); S. 69th St.(WT410190623), W. Arthur Av. to W. Cleveland Av.(30 working days); W. Harrison Av.(WT410190625), S. 67th St. to S. 71st St.(35 working days); S. 67th St.(WT410190626), 150’ N/O W. Finger Pl. to W. Harrison Av.(14 working days). Lead Service Line Replacements (WK64409154), at multiple locations throughout the project limits (working days included in individual relay projects). (Note: Contractor to furnish and install approximately 9,084 lin. Ft. of 12”, 8”, and 6” ductile iron pipe and perform approximately 2 Lead Service Replacements installing approximately 67 lin. Ft. of copper water service, Private Side Only. City to furnish miscellaneous materials as shown on plans and proposal form.)