Specifications include, but are not limited to: Crack seal, asphalt seal and stripe all areas as indicated on the plans a. Apply crack seal, asphalt seal and striping as per manufacturs recommendations. b. Striping is only required for areas that have been disturbed. c. Sealing and striping should be completed after the asphalt work has been completed. b. Remove and replace deteriorated areas of asphalt in City Park and Southwood Park. Refer to provided maps for both City Park and Southwood Park for locations of “mill and fill” areas. a. Mill areas as specified on plans (1.5 inches). b. Re-pave milled areas with asphalt wearing course (1.5 inches). c. Some locations are within the sealing areas, these locations should be sealed after asphalt has been placed. ; t remove existing landscaping planter and replace with asphalt wearing course (6 inches). ; alt wearing course (1.5 inches) is to be placed. Stripe parking lot after wearing course is placed.