Specifications include, but are not limited to: Paving at Art Shop Office Paving at Basketball Court Paving at Fire Escape Parking Paving at Dumpster Area ( Alternate 1 ) Paving Adjacent Area to Basketball Court ( Alternate 2 ) Paving Roadway ( Alternate 3 ) Sealcoat Basketball Court ( Alternate 4 ) 13.1.1 Mill area along upper side approximately 82 linear feet to provide a smooth transition between new and existing pavement. 13.1.2 Clean all loose dirt, rock, and grass from area. 13.1.3 Excavate area at building corner approximately 12 foot by 12 foot to a depth of 10 inches. 13.1.4 Compact subbase with Typar (Or Equal) stabilization fabric, 4” class I stone, paving with 2 ½ inch hot mix asphalt base course. 13.1.5 Paving area approximately 82 foot by 12 foot and newly excavated area with 2 ½ inch hot mix asphalt base course. 13.1.6 New pavement must be flush with existing concrete curb. 13.1.7 Required thickness is after compaction. 13.1.7 All work inclusive of but not limited to materials and installation must meet WVDOH Specifications.