Specifications include, but are not limited to: furnish all transportation, labor, supervision, equipment, tools, parts, scaffolding and materials, as necessary, to replace one (1) cable tray hanger and replace one (1) personnel access ladder located in the tank area under the bascule pit floor of the West Bound Berkley Bridge. 1. Upon VDOT issuance of a Notice to Proceed, take measurements necessary to fabricate one new cable tray hanger and one new personnel access ladder. 2. Provide Sketches to VDOT for Approval. 3. After receipt of VDOT Approval, order materials. 4. After receipt of materials, fabricate one cable tray hanger and one personnel access ladder. 5. Request VDOT inspection in the Contractor’s Shop. 6. After VDOT Approval of the fabrications, schedule for installation. 7. Install scaffolding. 8. Provide temporary support for the cable tray. 9. Remove and salvage the existing cable tray support. 10. Remove and salvage the existing ladder. 11. Install the new cable tray support. 12. Remove the temporary cable tray support installed in No. 8 above