The purpose of this requirement is to:
-
Shutdown and disconnect electrical and drain the existing water-cooled chilled water system
-
Provide and install new air-cooled chiller
-
Reconnect to existing water piping and provide and install new aluminum jack and new piping insulation
-
Add two tees and isolation valves for temporary chiller hook ups
-
Reconnect to existing electrical
-
Reconnect to existing controls
-
Receiving, storage, delivery and crane/rigging is included
-
Heat trace hook up and installation included for piping freeze protection, insulate label, strap and support pipes
-
Factory Start up and commissioning included
-
Refill system, leak check, bleed air, and return system to operation
-
Work to be performed during regular working hours.
-
Disposal of old air-cooler equipment and parts
At General Smalls Inn, Ft Eustis. Please review the attached Statement of Work for more information.
A site visit will be accomplished Jul 9, 2025 at 10:00 AM EST. If you require a pass to access the facility for this visit, please contact A1C Rebeca Ruji at rebeca.ruji.1@u.af.mil to ensure quick processing of your requests NLT COB July 7, 2025.
Questions are due July 3rd, 2025.
Quotes are due July 11, 2025.
Submit all inquiries quotes and site visit attendees info by email to A1C Rebeca Ruji at rebeca.ruji.1@us.af.mil.