Specifications include, but are not limited to: BEGINNING AT A POINT IN THE TOWN OF BARRE, ON MILL STREET, APPROXIMATELY 340 FEET WESTERLY OF THE VT ROUTE 110 / MILL STREET INTERSECTION, AND EXTENDING EASTERLY TO THE INTERSECTION OF VT ROUTE 110. WORK TO BE PERFORMED UNDER THIS PROJECT INCLUDES THE RECONSTRUCTION OF MILL STREET ON A REVISED ALIGNMENT, WITH NEW DRAINAGE, SIDEWALK, SIGNAGE, STRIPING, MINOR RECONSTRUCTION ON VT ROUTE 110, AND OTHER HIGHWAY RELATED ITEMS. 201.10 0005 CLEARING AND GRUBBING, INCLUDING INDIVIDUAL TREES AND STUMPS 1.000 LS 203.15 0010 COMMON EXCAVATION 1,645.000 CY 203.16 0015 SOLID ROCK EXCAVATION 25.000 CY 203.28 0020 EXCAVATION OF SURFACES AND PAVEMENTS 45.000 CY 203.31 0025 SAND BORROW 375.000 CY 204.20 0030 TRENCH EXCAVATION OF EARTH 320.000 CY 204.21 0035 TRENCH EXCAVATION OF ROCK 15.000 CY 204.22 0040 TRENCH EXCAVATION OF EARTH, EXPLORATORY (N.A.B.I.) 1.000 CY 204.30 0045 GRANULAR BACKFILL FOR STRUCTURES 30.000 CY 210.10 0050 COARSE-MILLING, BITUMINOUS PAVEMENT 1,670.000 SY 301.35 0055 SUBBASE OF DENSE GRADED CRUSHED STONE 840.000 CY 402.12 0060 AGGREGATE SHOULDERS 16.000 TON 404.65 0065 EMULSIFIED ASPHALT 8.000 CWT 406.35 0070 SUPERPAVE BITUMINOUS CONCRETE PAVEMENT 440.000 TON 406.38 0075 HAND-PLACED BITUMINOUS CONCRETE MATERIAL, DRIVES 170.000 SY