Specifications include, but are not limited to: Mill Run Pump Station (Generator & Automatic Transfer Switch– Mill Run Condos, Quechee Main Street) a.Town of Hartford shall provide excavation, backfill and site restoration. b.Contractor shall provide a poured in place concrete pad with reinforcement, anchor(s), and properly aligned and sized conduits. The contractor at a minimum shall follow the below steps. b1.Contractorshallutilizethemanufacturer’sstubupdrawingsfor the skid frame or subbase tank and compare these to the weather enclosure elevation drawing. The skid frame and/or subbase tank rest on the pad. The weather enclosure mounts above the skid/tank, and is your longest dimension, but does not rest on the pad. The entire unit shall be centered on a longer pad. b2. The contractor shall provide a sketch of the equipment using start of enclosure, start of skid/tank, end of skid/tank and end of enclosure as the reference points. The contractor shall use drawings to verify your conduit location is correct on the sketch.