Specifications include, but are not limited to: This project consists of but is not limited to: 1. Disconnect existing piping connections. 2. Disconnect existing electrical and control connections. 3. Remove and dispose/recycle one existing bollard and other removed unused materials. 4. Remove and dispose/recycle existing chiller. 5. Provide 24" wide x 4" deep reinforced concrete pad extension doweled into existing pad with two new bollards. 6. Provide two (2) new 6" capped tees cut into existing 6" CWS and R for temporary chiller plug-in. Provide 6" isolation valves below Tees. 7. Provide new circuit in MC conduit to panel and 460v 225-amp breaker with locked Nema 4 disconnect for temporary chiller hookup. 8. Provide new 70 Ton Chiller. 9. Deliver, rig and set new chiller. 10. Provide new electrical connections and wiring back to panel in existing conduit. 11. Provide new 3 pole, 460V, 250-amp breaker replacing existing. 12. Provide 6" insulated piping extensions and connections to new chiller with valves and flex connector. 13. Reconnect existing control connection. 14. Commission chiller. 15. Provide training to BGS staff. 16. Provide Operations and Maintenance Manual.