Specifications include, but are not limited to: e design and fabrication of seven tubular steel pole structures that will support the installation of transmission and distribution circuits; Six poles will be used to be part of the lines that will provide 138 kV potential to our future Mountain Vista substation and will support the distribution circuits coming out of the substation. These structures shall be direct embedded where feasible instead of concrete pier foundation. Coordination with city engineer required for the final design. The other pole will be used to house a new 46kV transmission line 3-way switch close to the intersection of Freedom Blvd and University Pkwy in Provo, UT. Due to site constraints, this structure will be required to be direct embedded