Specifications include, but are not limited to: demolishing the existing 100,000 gallon ground water storage tank and replacing with two 151,000 gallon ground water storage tanks piped and valved to allow each tank to be removed from service for maintenance and installing a pump station. The new ground water storage tanks will be directly connected to the new booster pump station intake line. The pump station discharge line will be connected to the water distribution system and be regulated by two new hydro pneumatic pressure tanks. The new pump house includes the construction of the building, plumbing and all electrical/mechanical controls, panels and pump room equipment. All work shall be performed as shown in the construction plans prepared by Charles Gojer & Associates,