Specifications include, but are not limited to: Construction of a 1.0 million gallon composite elevated storage tank, a booster station package, a flow meter assembly, all associated onsite plant piping, SCADA, electrical services and wiring and connections, and onsite grading, paving, and drainage improvements. Also included is the offsite construction of approximately 2,700 linear feet of 12-inch waterline, and 2,250 linear feet of 16-inch waterline, an access road to the site, and electrical service on the site. The City anticipates the following items will be included in the scope of the Project: site preparation; excavation; groundwater controls, SWPPP, pipe installation, tank construction, pump station construction, electrical construction, onsite and offsite water main construction; and all other appurtenances necessary for the complete Project. The Project will be designed and constructed so as to meet all applicable federal, state, and local accessibility standards.