Specifications include, but are not limited to: 1. Design and pre-construction phase: a. Regularly attend meetings with Harris County prior to construction and consult with Harris County regarding selection of systems and equipment. b. Develop a major task-based bar schedule. c. Develop a provisional construction project manager schedule indicating methods and sequencing of construction. Include time requirements for sequences and durations, milestones dates for receipt and approval of pertinent information, preparation and processing of shop drawings and samples, delivery schedule of materials or equipment requiring long-lead time procurement, project procurement schedule, and installation and construction completion. This includes the periodic updates of project schedule for review and Harris County approval