Specifications include, but are not limited to: The Contractor will be limited to work on only the following items in 2018: PCN X03M • Water Phase 1Ae work between Station 26+50 and 35+50 that does not affect traffic • Water Phase 1Af • Water Phase 1Be (E. St. Louis Street) sanitary sewer and Water Phase 1Af sanitary sewer work between Station 30+30 and 35+50 with the following restrictions: o No work in East Boulevard that affects traffic prior to August 13, 2018 o If the Contractor cannot complete all work within applicable restrictions for permanent surfacing, temporary surfacing on East Boulevard shall be either temporary asphalt or concrete. Temporary surfacing on East St. Louis Street shall be temporary asphalt or concrete. • Water Phase 2Bd • Storm Sewer Basin 22 grading, pipe, structure, and associated reclamation with the following restrictions: o If the Contractor cannot complete all work within applicable seasonal restrictions for permanent surfacing, temporary surfacing on East Boulevard North shall be temporary asphalt or concrete. Temporary surfacing within the North Maple Street cul-de-sac may be temporary gravel surfacing. PCN 02SF & 0515 • Detention Basin/Water Quality Basin in the northeast quadrant of East Boulevard and Omaha Street that does not affect traffic. PCN X03M Water Phase 2Ba Work Restrictions The Contractor may begin work on Water Phase 2Ba at any time. Once the Contractor begins work on the Water Phase 2Ba portion of the project, the Contractor will continue work to completion including, but not limited to; final surfacing, final restoration, permanent sidewalks, etc. The Department will not allow the Contractor to place temporary surfacing, restoration, sidewalks, etc. in the Water Phase 2Ba portion of the project.