Specifications include, but are not limited to: Scope of work is to refurbish the boys and girls restrooms in building #3 at Mayo High School, 405 Chestnut Drive, Darlington SC 29532. Contractor is to provide materials and labor to tear out and replace the floor and one sheetrock wall in each restroom, each restroom is approximately 18’ X 8’ (144 square feet). Contractor is responsible for removing and safely storing all toilets, sinks and urinals so they can be reused. The tear out of the floor will require removal of an epoxy sprayed on floor and terracotta laid on concrete. Both floors will need to be removed and concrete releveled for ceramic or porcelain tiles. Remove sheetrock wall behind sinks and urinals down to old block wall. Maintain present plumbing lines in floor and walls and evaluate any lines exposed during demolition for possible replacement with DCSD approval.