Specifications include, but are not limited to: 1. Clemson University will provide all concrete through an existing contract. 2. Clemson University will provide concrete pumping if necessary. 3. All flatwork projects 6” thick or less that is less than 700 square feet total area will use hourly rates and Clemson University will provide forming materials. 4. All 6” X 18” curb and gutter projects less than 120 linear feet total will use hourly rates and Clemson University will provide forming materials. 5. Any work not covered by unit pricing will be billed based on hourly rates. 6. Concrete finish: A smooth, hard, dense surface is desired, floating should be followed by steel troweling. Troweling should not be done on a surface that has not been floated; only bull floating is not an adequate finish procedure. A light broomed finish is desired, the concrete should be sufficiently hard to retain the scoring impression.