Specifications include, but are not limited to: Tower A/Administration 1. Repair defects in exterior insulation and finish system (EIFS) cladding and all associated miscellaneous work as specified herein. 2. Provide and install new weep screed where EIFS terminates at grade at Tower A and Administration Building. 3. Repair concrete spalls at columns and all associated miscellaneous work as specified herein at Tower A. 4. Provide and install new breathable weatherproof coating over all EIFS cladding and all associated miscellaneous work as specified herein at Tower A. Tower B/C 1. Repair all structural cracks 1/16 inch or larger in precast concrete panels with epoxy injection method and all associated miscellaneous work as specified herein. 2. Remove and replace all backer rod and sealant between precast concrete panels and around all wall penetrations (louvers, pipe penetrations, etc.) and all associated miscellaneous work as specified herein.