Specifications include, but are not limited to: The work to be completed consists of furnishing all materials, equipment, and labor necessary to construct approximately 3,160 linear feet of 6”, 10” and 12” water line relocation improvements, 5,100 linear feet of 6”, 8”, and 12” sewer force main relocation improvements and appurtenances in coordination with the roadway improvements by a contractor procured separately by the SCDOT, as shown in the plans and technical specifications to complete the project. The successful bidder will be provided a portion of the roadway project that has been cleared, and grubbed for installation of the utility improvements during the 120 day period of January 2, through May 2, 2019. The SCDOT road contractor’s schedule is not flexible, and the successful bidder for the utility relocation work must work within the schedule dictated by the SCDOT road contractor.