Specifications include, but are not limited to: o provide a design for a Central Generator Station to back up the two 4160 Volt feeders that serve the Roger Williams Complex (RWC), with provisions for backing up other feeders from substation 1 and 2 in the future. ;Three (3) – 4160 Volt, 1MVA diesel generators with two units installed initially and provisions for a third generator that will be installed at a later date. Each genset will be provided with an under mounted fuel oil tank capable of providing 48 hours of operation ; • DC Batteries for control power • Space for a racking mechanism • Space for a ground and test device (which should also be required in the design) • Space for a single data center type rack for a power management system ; • The first VFI switchgear (VFI-ATS1) will be used to intercept the existing 5kV feeder from Substation #1 to the existing VFI1-1, with one input from the new paralleling switchgear and the other input from Substation #1. The output will refeed the loads presently served from VFI-1-1.